Monday, July 6, 2009

weeks 13 & 14: pre-sheetrock inspection & insulation

This week the different trades were still gearing up for the presheet-rock inspection. Everything had to be done and in order so that the inspector would approve the project for insulation. He will also need to approve the insulation once it’s installed.

Minh and Ron of Anctil Heating and Cooling were here late to make sure all the ceiling and wall fans and dryer duct were properly vented. To economize space, we used one inline fan unit to vent both the bath and laundry and hid the exhaust under the deck. Usually, this type of fan is used in an attic, but it worked perfectly for our situation.

We also wanted to vent the AV Room to prevent heat build-up by the electronic equipment. Unfortunately, we could not determine where to place the exhaust because of the tight configuration. Originally we hoped to vent this fan through the utility chimney, but there was not enough space to fit another sleeve (the water heater vents here as well). Minh solved the problem by running the vent the opposite direction and exhausting the AV Room fan under the front porch. Thanks Minh. You rock!



Chad from Crestwood Inc. came by to fine-tune the cabinetry design. He looked at the style of the existing built-ins and determined what details would look nice for the new cabinetry. Chad had the shop drawings prepped the following week. We can’t wait for the real thing!

Daniel and Bob of Premier Plus Construction Inc. blocked out the bath and laundry sinks, the water turn offs and medicine cabinet, removed more dirt, cut out the old stray piping, framed in the kitchen drain and cleaned the entire job site. They had everything looking pretty tidy for the inspector. And a happy inspector is what we all want!




The pre-sheetrock inspection went smoothly. The inspector pointed out some missing fireblocking and a slightly drippy faucet, and had us secure some loose gas piping (so that it would not get damaged during construction). The plumbing and water service had already passed inspection, and were not a concern this round. The framing, electrical and HVAC easily passed as did the stairs, which had been a concern of mine from the beginning. Daniil of Anctil Plumbing took care of the faucet right away. Daniel and Bob of Premier Plus Construction Inc. installed the fireblocking. Erik our contractor of Ostmo Construction cleaned up the ceiling and foamed the holes in the ceiling joists. Now we were ready to insulate.

Phil and his team from Knez Insulation Company LLC insulated the basement in half a day. Besides insulating the exterior walls and wine cellar, we insulated the laundry, bath, furnace room and basement ceiling for sound. That way any noise from the main floor will not travel between floors or from the laundry and bathroom.




Aaron
of Portland Metro Electric stopped by to make a couple of adjustments.

Dana, the finish craftsman from Guillory Construction, installed the exterior doors. Little did he know that he would also need to frame in one of the doors on the hottest day of the year. Thanks Dana!




The inspector came by and approved the insulation. Now we can rock! Sheetrock, that is.

Tune in next time for the wine cellar prep!


No comments:

Post a Comment